Rack Mount Installation: Dell™ PowerVault™ 120T DLT1 Autoloader User's Guide

Tools Required Installing the PowerVault 120T DLT1 Support Box Assembly 
Preparing the Rail Assemblies Rack Mounting Dual PowerVault 120T DLT1s 
Mounting the Rail Assemblies

This section contains a detailed description of the steps to install the PowerVault 120T DLT1 or dual PowerVault 120T DLT1s into a standard 19" rack mount assembly.


Tools Required


Preparing the Rail Assemblies


Figure 1. Rail Position Detail


Mounting the Rail Assemblies


Figure 2. Mounting the Rail Assemblies

NOTE: The mounting flanges on the ends of the slide rail assemblies have to be positioned on the outside of the vertical mounting rails, and the rubber stop on the slide rail faces inward and toward the rear.


Installing the PowerVault 120T DLT1 Support Box Assembly


Figure 3. Installing the Support Box Assembly

The PowerVault 120T DLT1 is now ready for use.

Rack Mounting Dual PowerVault 120T DLT1s

The PowerVault 120T DLT1 has been designed so two units may be mounted side-by-side in a single rack slot. To add a second PowerVault 120T DLT1 to one currently mounted in a rack, follow these instructions: The PowerVault 120T DLT1 and the support box are secured to each other by a set of nut plates and four flathead screws. To separate the assemblies, remove the screws that secure the support box to the nut plates. One nut plate is accessible from the middle rear panel. The other nut plate is accessible from the bottom front panel.


Figure 4. Nut Plate Location on the Support Box
 


Figure 5. Separated PowerVault 120T DLT1 #1
 


Figure 6. Joining the Left and Right PowerVault 120T DLT1s
 


Figure 7. Securing the Flat Head Screws
 

The PowerVault 120T DLT1 units are ready for use.